INDUFLOOR®-ST1100

SPECIAL PRIMER

Properties:

  • Two component, low solvent, moisture tolerant epoxy resin.
  • Water vapour impermeable.
  • Due to its high density, INDUFLOOR®ST 1100 displaces the water from the surface capillaries of concrete substrates and acts as a barrier to oil rising through capillary action.
  • Forms a very good bond to damp concrete substrates. Prevents penetration of radon.

Application Method:

Using a rubber squeegee, apply ASODUR-SG2 to saturation onto the cleaned, matt damp substrate and thoroughly work into the surface with a priming brush and back roll with a short nap paint roller. Blind the fresh primer with quartz sand (grain size: 0.5 – 1.0mm diameter). Once hardened, carefully remove all non-bound quartz sand before subsequent coatings are applied to the primer.

Primary Uses :

  • As a special priming treatment for oil-contaminated but previously cleaned concrete substrates.
  • As effective protection against the formation of osmosis bubbles when there is moisture
    penetrating from the rear.
  • As a capillary breaking grout to the pool edge with high-level water tables, up to 1:1 filled with 0.1–0.6 mm quartz sand.
  • As a priming treatment for concrete/bonded screeds that are still damp, which are to receive floor coverings such as PVC, linoleum, carpet, parquet, tiles etc. Please refer to the advice section.
  • As a primer for SOLOPLAN® 30-PLUS.

Technical Data:

  • Basis: two-component epoxy resin.
  • Color:light grey..
  • Viscosity:70 s in a 4 mm DIN standard cup..
  • Mixture Ratio:100:12 parts by weight.
  • Density:1.86 g/cm3..
  • Pot Lifeapprox. 60 minutes at +23ºC, approx. 30 minutes at +30ºC.
    .

Product Details

It is essential that there is at least 8 cm

It is essential that there is at least 8 cm coverage of concrete from the side exposed to water. Bond AQUAFIN-CJ6 with a mounting adhesive suitable for waterstops. Completely cover the prepared substrate with the mounting adhesive and press the AQUAFIN-CJ into the adhesive until it oozes out from beneath. Do not begin the concreting process for at least 8 hours after bonding.

Waterstop connections can be made

Waterstop connections can be made by overlapping by 50 mm or by butt jointing. The waterstops must be placed tightly together to prevent gaps. But jointed waterstops must be covered by a separate section of waterstop with a 30 mm overlap to both sections.